Civil Construction Review Schedule

  • First and second construction drawing review submittals and revisions must be submitted on Mondays by noon for a two-week review cycle with comments going out Tuesdays (14 days after submittal date).
  • Subsequent submittals and revision reviews (after second review) must be submitted on Wednesdays by noon for a one-week review cycle with comments going out Thursdays (7 days after submittal date).

For questions or additional information, please contact the Holly Springs Engineering Department at (919) 557-3938.