School Days Lane Waterline

Project description:

Adding about 1,100 feet of 16-inch diameter water line to the Holly Springs Road water tank, improving system-wide performance and emergency connections with neighboring towns.

Location:

From water tank off School Days Lane to Holly Springs Road.

Status:

In design; pending easements

Estimated construction start:

2019

Public engagement:

Staff is in contact with the property owner.