Transportation Bond-Funded Project
Adding new right turn lane southbound from Avent Ferry Road to South Main Street, improving traffic flow onto South Main Street.
Location:
N.C. 55 southbound from Avent Ferry Road to Main Street
Status:
Completed
- Signed contract with design consultant Summit Design & Engineering Services
- Geo technical investigation
Underway
- 25% completion stage of plan
- Utility coordination
- Public meeting scheduled for Dec. 3 (25% plan completion)


Estimated construction start:
2020
Public engagement:
A public engagement meeting was held July 16 at Holly Springs Town Hall.
Another public engagement meeting to view the updated plan is scheduled for Dec. 3, 5-7 p.m. at Town Hall. Details
Next steps:
- 2020: Construction begins
Key partners:
Holly Springs staff has engaged with key partners for this project, including:
- North Carolina Department of Transportation
- Capital Area Metropolitan Planning Organization
- Duke Energy
- United States Army Corps of Engineers/North Carolina Division of Environmental Quality
Contact:
Holly Springs Engineering: (919) 557-3938